Migration Parallel-Run Cost Calculator

See what paying for the old estate and the cloud at once costs, and the month savings start.

Multi-cloudCalculatorA few numbers
New here? See what this tool does and how to use it.

Learn more

Migration Parallel-Run Cost Calculator

What this free tool does for you

Budget the months you pay for the old estate and the cloud at once, and know the month the move starts to pay for itself, before the plan is signed off.

How to use it

  1. Pick a scenario under Start from a scenario, or enter Today's bill a month and the Cloud bill a month, once moved.
  2. Set the Migration timeline and the Migration waves; the volume calculator can supply both.
  3. Under The overlap, say how early each wave's cloud is built and how long the old servers are kept after cutover.
  4. Set the Fixed share of today's bill: lease, power and staff that stop only when the last wave leaves.
  5. Read the Extra cost of the migration period, then Month by month to see where the two bills overlap.

Good to know

  • The exit date is the lever. Fixed costs end when the last wave is decommissioned, so a late exit costs more than a late first cutover.
  • Payback needs the one-time cost. Enter the One-time migration cost and the page tells you the month the savings have covered it.
  • Save or share. Use Copy link to this result to get a link with your numbers filled in.
Start from a scenario

Each one fills in the fields below for a typical workload of that kind. You can change any of them.

The overlap

Optional

Extra cost of the migration period$94,000.00
Months both estates run
7
Peak month
$60,666.67
Saving a month after
$10,000.00
Pays back
Month 18

8 months from the first wave to the last decommission.

Extra cost of the migration period
$94,000.00
Over 8 months you pay $264,000.00 for the old estate and $150,000.00 for the cloud, $414,000.00 in all, against $320,000.00 to stay put.
Old estate paid
$264,000.00
Until month 8, when the last wave is decommissioned.
Cloud paid
$150,000.00
During the same months, from each wave's build.
Staying would have cost
$320,000.00
$40,000.00 a month for 8 months.
After the move
$30,000.00/mo
$10,000.00 a month less than today.

Month by month

Old estateCloudToday’s bill
  1. Month 1Old estate only$40,000.00
  2. Month 2Wave 1 cuts over$50,000.00
  3. Month 3$50,000.00
  4. Month 4Wave 2 cuts over$60,000.00
  5. Month 5$50,666.67
  6. Month 6Wave 3 cuts over$60,666.67
  7. Month 7$51,333.33
  8. Month 8$51,333.33
  9. Month 9Cloud only$30,000.00

The last row is the first month with the old estate gone. Download the CSV for the figures by estate.

What this means

  • Pays back in month 18

    After month 8 you pay $30,000.00 a month, $10,000.00 less than today. That repays the $94,000.00 the move cost above staying by month 18.

  • Each month the old estate stays after cutover costs about $30,000.00

    You keep each wave's servers for 2 months after it moves. A shorter rollback window, or notice given before cutover rather than after, brings the exit date forward by the same amount.

  • Fixed costs run on for $48,000.00 after the first wave is gone

    30% of today's bill (lease, power, support contracts, staff) does not shrink wave by wave. It ends with the last decommission, so the exit date is the number that moves it.

  • Building each wave a month before cutover costs about $30,000.00

    The environment is paid for while it is tested and idle. Worth it for a safe cutover; keep the window as short as the team can test in.

What this model assumes

Show
  • Month 1 is the month the first wave starts, or the first month the cloud is built when the build lead is longer than the first wave’s slot. Waves are equal shares of the estate and cut over at even intervals along the timeline, each at the end of its month.
  • The cloud is paid for from the build. Each wave’s share of the cloud bill starts the stated number of months before its cutover, at full size, and runs on after it.
  • The old estate shrinks wave by wave, except its fixed share. Each wave’s share of today’s bill stops the stated number of months after its cutover; the fixed share stops when the last wave does.
  • Payback counts savings against staying put, month by month, from month 1, until they cover the extra cost of the period and the one-time cost.
  • Not counted: the transfer itself (the transfer cost comparator prices it), licenses that must be bought twice, hardware resale, and discounts that start later than the bill.

Planning the exit?

Cloud Cost Audit: We review the wave plan, the decommission dates and the target bill before the overlap starts, so the months of double running are the ones you planned. From $1,500, fixed. Nothing paid upfront.

See the service

Questions

What is parallel running in a cloud migration?

The months when the old estate and the new one are both paid for. Each wave's cloud environment is built and paid for before it cuts over, and its old servers are kept for a rollback window after. Lease, power and staff costs do not shrink wave by wave; they stop when the last wave is decommissioned.

How much does parallel running cost?

Add the old bill and the cloud bill for every month until the old estate is gone, then take off what staying put would have cost. A $40,000 a month estate moving to a $30,000 cloud bill in three waves over six months, built a month early and kept two months after, costs $94,000 more than staying over eight months.

When do cloud migration savings start?

Not at the first cutover. The monthly bill falls below today's only once enough of the old estate is switched off, and the overlap is repaid later still: in the example above the bill drops to $30,000 in month 9 and the move has paid for itself by month 18.

Why does the old bill not fall when the first servers leave?

Because part of it is fixed: the data center lease, the power contract, support agreements and the people who run it. Those costs end on the exit date, not when a rack empties, which is why the exit date moves the total more than the first cutover does.

How long should the old estate be kept after cutover?

As long as a rollback is realistic, and no longer. Every extra month costs that wave's share of today's bill. Give notice on contracts before cutover rather than after, and set a decommission date with an owner for each wave.

Related tools

More tools for: Compute and utilization

The overlap ends. The cloud bill does not.

Finitizer reads the new estate's bill from the first month, by workload, so the cloud figure in this plan is checked against what you are actually paying.

See how Finitizer works